Here are the different ways to change the resource assigned to work.



To reassign all segments


Select the reassign resource option.



Select a resource to assign the work to or use check availability to browse for alternative resources based on their availability.








To reassign a single segment


Click an assignment bar.




Select re-assign.





Select the resource selector.




Select a resource to re-assign the work to (you can also select an alternate project and sprint to move the work to).


Select re-assign.