When entering work into Kelloo, the work type can be set as agile or standard


If set to agile, the remaining work can be entered in days, points or FTE. If set to standard, the remaining work can be entered in days or FTE.


Here are the different ways to update remaining work:



Click the resource assignment you want to update.





Then enter the remaining work





Or, click the resource assignment name in the left grid.





Decide if you want to enter work in days / hours, points or FTE.




Then enter the remaining work in the work details panel.




You can select all work settings for advanced scheduling options such as days per week.




If work is entered in points, Kelloo uses the sprint points per day setting to calculate how many days this equates to. Override the sprint points per day setting by clicking the link.



If work is entered in FTE then Kelloo works out how many days this equates to and uses the sprint points per day to calculate the points this equates to.